Calculadora de Cronograma de Proyecto Gratis
Planifica el cronograma de tu proyecto. Calcula fechas de entrega considerando tareas, dependencias y recursos.
hrs
hrs/week
%
Weeks Needed
8 weeks
Months (approx)1.7 months
Total Hours (with buffer)144 hrs
Weeks Needed vs Total Effort (Hours)
Fórmula
## How to Estimate a Project Timeline Divide total effort by weekly available hours, then add a buffer for unknowns and scope changes. ### Formula **Buffered Hours = Effort x (1 + Buffer %)** **Weeks = Buffered Hours / Hours Per Week**
Ejemplo Resuelto
120-hour project, working 20 hours/week, with 20% buffer.
- 01Buffered hours = 120 x 1.20 = 144 hours
- 02Weeks needed = ceil(144 / 20) = 8 weeks
- 03Months = 8 / 4.33 = 1.8 months