Kostenloser Project Timeline Rechner

Schätzen Sie how many weeks a project will take. Factor in available hours und a buffer for unexpected delays.

hrs
hrs/week
%

Weeks Needed

8 weeks

Months (approx)1.7 months
Total Hours (with buffer)144 hrs

Weeks Needed vs Total Effort (Hours)

Formel

## How to Estimate a Project Timeline Divide total effort by weekly available hours, then add a buffer for unknowns and scope changes. ### Formula **Buffered Hours = Effort x (1 + Buffer %)** **Weeks = Buffered Hours / Hours Per Week**

Lösungsbeispiel

120-hour project, working 20 hours/week, with 20% buffer.

  1. 01Buffered hours = 120 x 1.20 = 144 hours
  2. 02Weeks needed = ceil(144 / 20) = 8 weeks
  3. 03Months = 8 / 4.33 = 1.8 months

Häufig Gestellte Fragen

How much buffer should I add?

10-20% for well-defined projects, 30-50% for projects with significant unknowns. Buffer absorbs scope creep, debugging, and unexpected delays.

Why use available hours instead of total work hours?

Not all work hours go to a single project. Account for meetings, email, admin, and other projects when estimating available time.

How do I estimate total effort hours?

Break the project into tasks, estimate each one, and sum them. Use past projects as benchmarks. When in doubt, triple your initial gut estimate.