Calcolatrice Volume Movimentazione Terra Gratuita
Calcola i volumi di scavo e riporto.
m^2
m^2
m
%
Bank (in-place) Volume
1,500.0 m^3
Loose (truck) Volume1,875.0 m^3
Bank (in-place) Volume vs Cross-Section Area 1 (A1)
Formula
## Average End Area Method The average end area method estimates earthwork volume between two surveyed cross-sections. ### Formula **V = (A1 + A2) / 2 x L** where A1 and A2 are the cross-sectional areas at each station and L is the distance between them. For excavated material, apply a swell factor (typically 20-40%) because soil expands when dug out. The loose volume is what determines truck loads.
Esempio Risolto
Cross-sections of 25 m^2 and 35 m^2, 50 m apart, 25% swell.
- 01Bank volume = (25 + 35) / 2 x 50 = 30 x 50 = 1500 m^3
- 02Loose volume = 1500 x 1.25 = 1875 m^3
- 03Truck loads (10 m^3 per truck) = 1875 / 10 = 188 loads