Bank (in-place) Volume

1,500.0 m^3

Loose (truck) Volume1,875.0 m^3

Bank (in-place) Volume vs Cross-Section Area 1 (A1)

Formula

## Average End Area Method The average end area method estimates earthwork volume between two surveyed cross-sections. ### Formula **V = (A1 + A2) / 2 x L** where A1 and A2 are the cross-sectional areas at each station and L is the distance between them. For excavated material, apply a swell factor (typically 20-40%) because soil expands when dug out. The loose volume is what determines truck loads.

Esempio Risolto

Cross-sections of 25 m^2 and 35 m^2, 50 m apart, 25% swell.

  1. 01Bank volume = (25 + 35) / 2 x 50 = 30 x 50 = 1500 m^3
  2. 02Loose volume = 1500 x 1.25 = 1875 m^3