Infrastructure Cost Breakdown
Infrastructure is typically the single largest cost component in land development after the land itself. Accurate estimation is essential for project feasibility.
Major Components
Cost Variables
Bidding Strategy
Get at least 3 competitive bids from contractors, and include a 10-15% contingency for unexpected conditions.
हल किया गया उदाहरण
30-lot subdivision with $420,000 roads, $180,000 water, $210,000 sewer, $120,000 electric/gas, $95,000 stormwater, $60,000 landscaping.
- Total infrastructure: $420,000 + $180,000 + $210,000 + $120,000 + $95,000 + $60,000 = $1,085,000
- Cost per lot: $1,085,000 / 30 = $36,167
- Roads per lot: $420,000 / 30 = $14,000
- Water per lot: $180,000 / 30 = $6,000
- Sewer per lot: $210,000 / 30 = $7,000