Earthwork Volume CalculatorFormule

## Average End Area Method

The average end area method estimates earthwork volume between two surveyed cross-sections.

### Formula

**V = (A1 + A2) / 2 x L**

where A1 and A2 are the cross-sectional areas at each station and L is the distance between them. For excavated material, apply a swell factor (typically 20-40%) because soil expands when dug out. The loose volume is what determines truck loads.

Exemple Résolu

Cross-sections of 25 m^2 and 35 m^2, 50 m apart, 25% swell.

  1. Bank volume = (25 + 35) / 2 x 50 = 30 x 50 = 1500 m^3
  2. Loose volume = 1500 x 1.25 = 1875 m^3
  3. Truck loads (10 m^3 per truck) = 1875 / 10 = 188 loads