Calculateur de Dalle en BétonFormule

How to Calculate Concrete for a Slab

Concrete is ordered in cubic yards. To figure out how many you need, calculate the volume of the slab in cubic feet (length x width x thickness), then divide by 27 (since there are 27 cubic feet in a cubic yard). A standard 10x10 slab at 4 inches thick needs about 1.23 cubic yards before waste.

The Formula

Cubic Yards = (Length x Width x Thickness in feet) / 27

If your thickness is in inches, divide by 12 first to convert to feet. A 4-inch slab is 0.333 feet thick.

Always Add a Waste Factor

Order 5-10% extra. Concrete doesn't pour perfectly into forms. Some spills, some sticks to the truck, and ground surfaces aren't perfectly level. For a 3 cubic yard pour, order 3.3 yards. Running short mid-pour is much worse than having a little left over. Most suppliers won't deliver less than 1 cubic yard, and a short load fee applies if you order less than their minimum (usually 3-4 yards).

Typical Slab Thickness

  • Sidewalks and patios: 4 inches
  • Driveways (cars): 4-5 inches
  • Driveways (heavy vehicles): 6 inches
  • Garage floors: 4-6 inches
  • Shed foundations: 4 inches
  • Footings: 8-12 inches minimum (check local code)
  • Thicker isn't always better. A well-compacted 4-inch slab on proper base material can handle most residential loads. But if the subgrade is poor (clay, organic soil, or uncompacted fill), going thicker helps.

    Common Mistakes

  • Measuring in the wrong units. Mixing inches and feet in the calculation is the number one error. Convert everything to feet before multiplying.
  • Not accounting for the slab shape. L-shaped patios, curved sidewalks, and stepped foundations need to be broken into rectangles and calculated separately.
  • Ordering too close to exact. Concrete suppliers charge the same whether you use the last 0.25 yards or not. Having a wheelbarrow of extra is fine. Being half a yard short means a second delivery, cold joint, and a weaker slab.
  • Exemple Résolu

    A patio slab measuring 20 ft by 12 ft with a 4-inch thickness.

    1. Convert thickness: 4 inches / 12 = 0.333 ft
    2. Volume = 20 × 12 × 0.333 = 80 cu ft
    3. Cubic yards = 80 / 27 = 2.96 cu yd
    4. With 10% waste = 2.96 × 1.10 = 3.26 cu yd
    5. Order 3.5 cubic yards from the concrete plant.