Project Cost Calculator Formula
Understand the math behind the project cost calculator. Each variable explained with a worked example.
Formulas Used
Subtotal (before contingency)
subtotal_display = subtotalContingency Amount
contingency_amount = subtotal * contingency_pct / 100Total Project Cost
total_cost = subtotal * (1 + contingency_pct / 100)Variables
| Variable | Description | Default |
|---|---|---|
labor | Labor Costs(USD) | 12000 |
materials | Material Costs(USD) | 8000 |
equipment | Equipment Costs(USD) | 2000 |
overhead | Overhead Costs(USD) | 3000 |
contingency_pct | Contingency(%) | 10 |
subtotal | Derived value= labor + materials + equipment + overhead | calculated |
How It Works
How to Estimate Project Costs
Formula
Total Cost = (Labor + Materials + Equipment + Overhead) x (1 + Contingency%/100)
A contingency budget covers unexpected costs, change orders, and price fluctuations. Industry standard is 5-15% depending on project complexity and risk.
Worked Example
A remodeling project with $12,000 labor, $8,000 materials, $2,000 equipment, $3,000 overhead, and 10% contingency.
labor = 12000materials = 8000equipment = 2000overhead = 3000contingency_pct = 10
- 01Subtotal = $12,000 + $8,000 + $2,000 + $3,000 = $25,000
- 02Contingency = $25,000 x 10% = $2,500
- 03Total project cost = $25,000 + $2,500 = $27,500