## How to Estimate Material Costs
### Formula
**Total = Quantity x Unit Cost x (1 + Waste%/100) x (1 + Markup%/100)**
Waste factor accounts for cuts, breakage, defects, and installation waste. Markup covers your profit and overhead on materials.
### Formula
**Total = Quantity x Unit Cost x (1 + Waste%/100) x (1 + Markup%/100)**
Waste factor accounts for cuts, breakage, defects, and installation waste. Markup covers your profit and overhead on materials.
计算示例
500 square feet of tile at $12/sq ft with 10% waste and 25% markup.
- Base material cost = 500 x $12 = $6,000
- Cost with 10% waste = $6,000 x 1.10 = $6,600
- Total with 25% markup = $6,600 x 1.25 = $8,250
- Quantity to order = 500 x 1.10 = 550 sq ft